AtkinsRéalis was commissioned to undertake a Constraints Study including advanced Bird Surveys and Screening for the need for an Appropriate Assessment, Environmental Impact Assessment and input into the Phase 1 Appeal Document for the proposed 2-phase, 70MW wind farm.
Our multidisciplinary team provided the following surveys and reports for the Environmental Impact Statement: Strategic Planning Context, Consultation (Statutory, non Statutory and Public), Traffic and Transport, Flora and Fauna, Water Quality, Soils and Hydrogeology, Cultural Heritage, Air Quality, Noise and Vibration and Shadow Flicker. Our skilled and experienced environmental team worked closely with our client to achieve planning permission for phase 1 of the development which will provide electricity supply for up to 30,000 homes per annum.
Client: Private